I-696 Restore the Reuther (Phase 2)

(Lahser Road to Dequindere)

I-696 Restore the Reuther (Phase 2)

(Lahser Road to Dequindre)
As of (November 24, 2026)

Current Construction & Traffic Updates

WB I-696 is OPEN and returned to the westbound lanes from I-75 to M-10 the Lodge.  

EB I-696 is scheduled to open to traffic by Monday 11/23/26 at 5 am.  This will include all associated entrance and exit ramps for EB I-696 with one exception.  The SB Telegraph to SB Lodge Freeway ramp will remain closed for approximately 2 additional weeks.

—–UPCOMING CLOSURES—–

EB I-696 is scheduled to open to traffic by Monday 11/23/26.

Church Street will remain closed through mid-December 2026.

The ramp from SB Telegraph to SB Lodge Freeway will remain closed for an additional few weeks to facilitate completion of work.  

 

Please continue to check back for up-to-date traffic updates.

 
For questions or comments, please call 248-930-1777

MAINLINE I-696 CLOSURES

EB I-696, M-10 to I-75, CLOSED through 11/23/26.
Detour: SB M-10 to EB M-8 (Davison) to NB I-75

LOCAL CLOSURES

EB Service Drive and WB Service Drives will have intermittent lane closures through mid-December.

Church Street will remain closed through mid-December.

BRIDGE CLOSURES

NB/SB Church St over I-696, CLOSED, through mid-December

 RAMP CLOSURES

M-10 (Lodge Freeway)

SB M-10 ramp to SB US-24, CLOSED, through 11/23/26

SB M-10 ramp to EB I-696, CLOSED, through 11/23/26

US-24 (Telegraph)

NB US-24 to EB I-696, RAMP CLOSED, through 11/23/26

SB US-24 to SB M-10, RAMP CLOSED, through mid-December

Lahser

NB & SB Lahser to EB I-696, CLOSED, through 11/23/26

Evergreen

NB/SB Evergreen ramp to WB I-696 is OPEN 

WB I-696 to Evergreen is OPEN 

EB I-696 to Evergreen, CLOSED, through 11/23/26

Evergreen to EB I-696, CLOSED, through 11/23/26

Southfield

EB I-696 to Southfield, CLOSED, through 11/23/26

Southfield to EB I-696, CLOSED, through 11/23/26

WB I-696 exit ramp to Southfield Rd is OPEN 

Southfield Rd entrance ramp to WB I-696 is OPEN 

Greenfield

NB/SB Greenfield ramp to WB I-696 is OPEN 

WB I-696 ramp to Greenfield is OPEN 

EB I-696 to Greenfield, CLOSED, through 11/23/26

Evergreen to EB I-696, CLOSED, through 11/23/26

Coolidge

WB I-696 ramp to Coolidge is OPEN 

Coolidge to WB I-696 is OPEN 

EB I-696 to Coolidge, CLOSED, through 11/23/26

Coolidge to EB I-696, CLOSED, through 11/23/26

M-1 (Woodward)

EB I-696 to Woodward, CLOSED, through 11/23/26

Woodward to EB I-696, CLOSED, through 11/23/26

WB I-696 off ramp to Woodward Ave is OPEN 

WB I-696 on ramp from Woodward Ave is OPEN 

Bermuda/Mohawk

WB I-696 to Bermuda/Mohawk is OPEN 

Campbell/Hilton

NB/SB Campbell/Hilton to WB I-696, OPEN on 10/16/26

EB I-696 to Campbell/Hilton, CLOSED, through 11/23/26

Campbell/Hilton to EB I-696, CLOSED, through 11/23/26

I-75

WB I-696 to NB and SB I-75 OPEN

EB I-696 to NB I-75, CLOSED, through 11/23/26

EB I-696 to SB I-75, CLOSED, through 11/23/26

Couzens

NB/SB Couzens to WB I-696 is OPEN 

WB I-696 from I-75 to M-10 is OPEN as well as all associated entrance and exit ramps.  

EB I-696 is scheduled to open to traffic by Monday 11/23/26 at 5 am.  This will include all associated entrance and exit ramps for EB I-696 with one exception.  The SB Telegraph to SB Lodge Freeway ramp will remain closed for approximately 2 additional weeks.

In 2027, EB/WB I-696 between I-75 and Dequindre will have construction and the freeway will remain open. Project information can be found at DrivingOakland.com. MDOT construction locations can be found at Michigan.gov/drive. PLEASE DRIVE SLOWLY AND SAFELY THROUGH WORK ZONES.